吉泽明步伦理片_国产黄色av_中文字幕人妻无码一夲道蜜桃_白丝校花在我腿上呻吟jk

Language:CHINESESENGLISH

Home > News > Guangzhou Steel teach you: hoisting steel construction zone safety of the general provisions
CONTACT US
  • Address:Pingtang Industrial District, Shipeng Village, Shishan Town, Nanhai District, Foshan City,
  • Phone:0757-81002668/0757-63323396
  • Fax:0757-81196682
  • Contact:Ben Zheng/13826981293 Kerry Lu/13751224830
  • E-mail:sbs@sbsprefabhouse.com
  • URL:http://m.medcpap.com

Guangzhou Steel teach you: hoisting steel construction zone safety of the general provisions

Time:[2015-7-29]  Hits:5208

Guangzhou Steel teach you: hoisting steel construction zone safety of the general provisions


1, lifting the region should set the security cordon, non-staff prohibited from entering.
2, lifting objects hanging from the ground 200mm ~ 300mm, should conduct a comprehensive inspection, and should officially lifted after confirmation.
3, when the wind speed reaches the 10m / s, should stop lifting work; when the wind speed reaches the 15m / s, shall lifting work.
4, high-altitude work using small hand tools and small parts should be taken to prevent the fall approaches.
5, the construction of electricity should be consistent with the current industry standard "construction site temporary electrical safety specifications" JGJ 46 of the relevant provisions.
6, the construction site should be professional personnel to install, maintain and handle electrical equipment and power lines.
7, every day hanging member when finished floor or roof is not installed on to, to be taken and reliable way for temporary fixing.
8, the pressure plate surface water, ice, frost or snow, should be promp

Copyright:佛山市勝邦鋼結構有限公司 Foshan Shengbang Steel Structure Co., Ltd. Record Number:粵ICP備13078463號